Document Library
MODULE 1: Eligibility Period
MODULE 2: Forming the Team
MODULE 3: Feasibility Study
Preferred Schematic Report (PSR) – TBD
Preferred Schematic Report (PSR) – TBD
The project team has now been established through the Fall Brook Building Committee and the Designer Selection Panel process. With the project team complete, the project now moves in to Feasiblity Study, starting with educational programming and intense studying of the existing building and site. The next step in the process was to complete the first submission known as the Preliminary Design Program (PDP) that was submitted to the MSBA for review on April 12. The next step is now to work on the Preferred Schematic Report (PSR) which is targeted for August 29. This report summarizes the preferred site and building option.
August 27, 2024
August 16, 2024
July 9, 2024
June 11, 2024
May 14, 2024
April 11, 2024
March 12, 2024
March 5, 2024
February 15, 2024
January 30, 2024
January 9, 2024
December 12, 2023
November 2, 2023
September 26, 2023