Document Library
MODULE 1: Eligibility Period
MODULE 2: Forming the Team
MODULE 3: Feasibility Study
Preliminary Design Program (PDP) – TBD
Preferred Schematic Report (PSR) – TBD
Preliminary Design Program (PDP) – TBD
Preferred Schematic Report (PSR) – TBD
The project team has now been established through the Fall Brook Building Committee and the Designer Selection Panel process. With the project team complete, the project now moves in to Feasiblity Study, starting with educational programming and intense studying of the existing building and site. The next step in the process will be to complete the first submission known as the Preliminary Design Program (PDP) that gets submitted to the MSBA for review. This submission is currently targeted for April 2024.
April 11, 2024
March 12, 2024
March 5, 2024
February 15, 2024
January 30, 2024
January 9, 2024
December 12, 2023
November 2, 2023
September 26, 2023