Fall Brook Elementary School

Building Project

Project News

The project team will attended the live broadcast of Inside Leominster on February 19 at 4pm. The show was aired on Leominster TV and can be viewed on YouTube at https://www.youtube.com/live/xLRIQ9ksqZw?si=QOlvW_WgilqqlSIz

The presentation below was also shown during the show.

Project Outreach

The project team (Leftfield and MDS) will also attend these upcoming local events and will be available to answer questions about the project.

City Council Public Schools Subcommittee Thursday, March 19, 2026, 5:30pm
Fall Brook Talent Show Thursday, March 26, 2026, 5:30-7:30pm
Fall Brook Spring Concert Thursday, April 30, 2026, 6:00-7:00pm

Project Timeline and Status

FEBRUARY 27, 2026

The project team submit 60% Construction Documents to the MSBA

DECEMBER 5, 2025

The project team submit Design Development to the MSBA

SEPTEMBER 29, 2025

City of Leominster executes the Project Funding Agreement with the MSBA

JULY 2, 2025

City of Leominster executes the project scope & budget agreement with the MSBA

APRIL 30, 2025

The MSBA Board of Directors approve the project to move forward with Project Funding Agreement, Detailed Design and construction

FEBRUARY 28, 2025

The project team submit Schematic Design to the MSBA

OCTOBER 30, 2024

The MSBA Board of Directors approve the project to move into Schematic Design

August 29, 2024

The project team submit PSR to the MSBA

April 15, 2024

The project team submit PDP to the MSBA

December 12, 2023

City of Leominster enlists MDS/Miller Dyer Spears Architects as their Designer

March 27, 2023

City of Leominster enlists LeftField, LLC as their OPM

December 21, 2022

MSBA invites City of Leominster to the Feasibility Study for Fall Brook Elementary School

June 23, 2021

City of Leominster submitted the Statement of Interest to the MSBA for the Fall Brook Elementary School project

Shortcuts

MSBA WEBSITE

Click here for more information about funding and protocols of capital improvement projects in the Commonwealth’s public schools

GLOSSARY OF TERMS

Click here for a reference guide to clarify context and meaning to common terms used in the building process for public projects

PROJECT UPDATES

Construction - Module 7

The project has now completed the Feasibility Study and Detailed Design module, and are now in Module 7 – Construction. This process started with the 60% Construction Documents phase which was completed in late February with a submission of drawings and specifications to the MSBA. The following step will now be 90% Construction Documents, followed by 100% Construction Documents, bidding and then construction. The current schedule has actual construction starting on site in Fall of 2026.

UPCOMING EVENTS

MOST RECENT EVENTS

QUESTIONS

CONTACT US
FAQs

Translate »