Fall Brook Elementary School

Building Project

TEST PAGE

MODULE 1: Eligibility Period

MODULE 2: Forming the Project Team

MODULE 3: Feasibility Study

PROJECT UPDATES

Construction - Module 7

The project has now completed the Feasibility Study and Detailed Design module, and are now in Module 7 – Construction. This process started with the 60% Construction Documents phase which was completed in late February with a submission of drawings and specifications to the MSBA. The following step will now be 90% Construction Documents, followed by 100% Construction Documents, bidding and then construction. The current schedule has actual construction starting on site in Fall of 2026.