Fall Brook Elementary School

Building Project

Fall Brook School partners with families and the community

to help every student reach their potential

in a safe, welcoming environment

$114,821,932
Total Project Budget

$89,759,943
Construction Budget

56.06%
Max MSBA Reimbursement

$16,233,110 Committed to Date as of May 31, 2026

$8,421,032 Spent to Date as of May 31, 2026

7% Completion to Date as of May 31, 2026

1% Construction Budget Spent to Date as of May 31, 2026

PROJECT UPDATES

Construction - Module 7

The project has now completed the Feasibility Study and Detailed Design modules, and are now in Module 7 – Construction. This process started with the 60% Construction Documents phase which was completed in late February with a submission of drawings and specifications to the MSBA. The following step was then the 90% Construction Documents, followed by 100% Construction Documents, bidding and then construction. The current schedule has actual construction starting on site in Fall of 2026, with early site and prep work starting in June 2026.